Long Beach ADU cost & timeline

These are the real ranges we build to in Long Beach and across Los Angeles County — not national averages. Detached ADUs run $180,000 to $350,000 depending on square footage, garage conversions run $90,000 to $145,000, and an ADU above a detached garage runs $195,000 to $400,000. Conversions take about 3 to 6 months to build; new construction takes 5 to 10 months.

Detached backyard accessory dwelling unit built in Long Beach, California

Detached ADU (new construction)

Cost range
$180,000 – $350,000
Build timeline
5 – 10 months of construction

A stand-alone unit in the backyard. Where you land in the range depends mostly on square footage, plus finish level and how far utilities have to travel.

  • New foundation, framing, roof, and full utility runs
  • Studio and 1-bedroom plans sit at the lower end
  • 2-bedroom and larger footprints move toward the top
  • Luxury finishes, vaulted ceilings, and site work add cost
Excavation and footings for a detached ADU foundation
1. Foundation dug and formed
Detached ADU walls and roof framed on the slab
2. Walls and roof framed
Finished garage conversion ADU interior with kitchen and laundry

Garage conversion ADU

Cost range
$90,000 – $145,000
Build timeline
3 – 6 months of construction

The most affordable path to a legal ADU. You reuse the existing slab and walls, so the money goes into structure, utilities, and finishes instead of a new shell.

  • Existing footprint keeps foundation costs down
  • Structural retrofit, shear panels, and insulation to current code
  • New kitchen, bathroom, laundry, and mini-split system
  • Sewer, water, and electrical upgrades as required
Original detached garage in Long Beach before conversion
1. Existing garage, before
Garage conversion with five feet added and new stucco exterior
2. Five feet added, new exterior
Finished ADU built above a detached garage in Huntington Beach, California

Above-garage / two-story ADU

Cost range
$195,000 – $400,000
Build timeline
5 – 10 months of construction

Adds living space over a detached garage without giving up yard. It carries the most engineering of the three, which is why the range is the widest.

  • Foundation and structural upgrades to the existing garage
  • Engineered stairs, landing, and second-floor framing
  • Often the best fit on narrow or fully used lots
  • Great for rentals, guest quarters, or a caretaker suite
Original detached garage in Huntington Beach before the ADU was built above it
1. Existing garage, before
Second-story framing above the detached garage
2. Second-story framing

Cost and timeline at a glance

ADU typeCost rangeBuild timeline
Detached ADU (new construction)$180,000 – $350,0005 – 10 months of construction
Garage conversion ADU$90,000 – $145,0003 – 6 months of construction
Above-garage / two-story ADU$195,000 – $400,0005 – 10 months of construction

Ranges cover design, permitting, and construction of the unit. Site-specific work such as grading, drainage, long sewer runs, or panel upgrades is quoted separately after we walk the property.

  • Permits, solar panels, fire sprinklers, fences, utility upgrades, appliances, and upgrades to original house not included.
  • During your consultation we walk through every exclusion in writing — we are fully transparent about what is not in the price so there are no surprises.

How the schedule actually runs

  1. 01. Design & plans

    We measure the lot, confirm what fits, and draw the unit.

  2. 02. Engineering & permits

    Plans go to the city; we answer corrections until approval.

  3. 03. Construction

    3–6 months for a garage conversion, 5–10 months for new construction.

  4. 04. Final inspections & handover

    Sign-offs, punch list, and keys.

Long Beach ADU questions

How much does an ADU cost in Long Beach?

A detached ADU runs $180,000 to $350,000 depending on square footage. A garage conversion runs $90,000 to $145,000. An ADU above a detached garage runs $195,000 to $400,000. Every project is quoted after we see the lot, the existing structure, and your plans.

How long does it take to build an ADU?

Garage conversions typically take 3 to 6 months of construction. New construction, including detached and above-garage units, typically takes 5 to 10 months. Design and permitting happen before that and add their own time.

What drives an ADU to the high end of the range?

Square footage first, then finish level, long utility runs, difficult site access, grading or drainage work, and second-story structural requirements.

Is a garage conversion cheaper than a detached ADU?

Yes. Reusing the existing slab, walls, and roof removes the most expensive part of new construction, which is why conversions start around $90,000.

Do you handle plans and permits?

Yes. We handle design, engineering, permitting with the city, construction, and final inspections as one contract, so there is one team accountable start to finish.

Want a number for your lot?

Send your address and what you have in mind. We'll tell you what fits, where it lands in these ranges, and how long it takes. You can also talk to a real person at (877) 969-CASA.